The agenda for the Ivins City Council's regular meeting on Thursday, November 19, 2026 (5:30 p.m., City Council Chambers, 85 N. Main St.) listed item 2F, “Department Reports: Building & Zoning; Public Works & Engineering; Finance.” Three written reports were attached to that item in the meeting packet: “Building Department Reports,” “Public Works Summary of Operations” and “Engineering Report.” This post summarizes what those staff documents state. They are reports to the Council, not Council actions, and minutes for the November 19 meeting had not been posted as of the morning of November 23, 2026, so nothing here describes any discussion or vote. The meeting is listed on the Ivins Meetings page.
Building Department: 2026 year-to-date summary
The Building Department Reports attachment opens with a “2026 YTD Building Construction Data Summary.” As listed there:
- Total permits: 298
- Residential permits: 63, with a total value of $41,785,645
- Additions permits: 17, with a total value of $1,870,955 (ADUs: 4)
- Multi-family permits: 0 ($0)
- Other permits (“water heater, AC/Furnace, gas lines, pools, porch/awnings”): 159, with a total value of $6,472,987
- Commercial permits: 19, described in the report's key points as “a total value of about $14.2 million”
- Solar permits: 40, with a total value of $1,438,217
- Total inspections completed in 2026: 6,444
The attachment also includes month-by-month permit tables for calendar years 2025 and 2026 and fiscal years 2026 and 2027, plus trend charts of single-family and multifamily permits. A note on the multifamily chart states that multifamily permit reporting “has historically included ‘hospitality’ units” and that in 2025 “a best-effort adjustment was made to distinguish multifamily housing units from hospitality units.”
Public Works: Summary of Operations for November 2026
The Public Works Summary of Operations lists, among other items:
- Water: water sampling at 12 locations for total coliform bacteria and chlorine residuals, “which meet our water quality standards”; 7 utility/billing work orders; 29 Public Works service requests; 3 new 5/8-inch residential meters installed; new services pulled at 6 locations; a water main repaired at 1 location; one fire hydrant replaced; and 250 metal meter lids replaced with plastic composite lids “to meet the requirements of our AMI system.”
- Sewer: weekly maintenance on the sewer lift station and dosing station, weekly inspections at the Coyote Gulch dosing station, and sonar testing with 947 manholes inspected.
- Streets: 3.3 tons of asphalt and 8 tons of roadbase used for street and shoulder repairs due to water leaks; 15 cubic yards of concrete and 20 tons of roadbase used to repair trip hazards; 1 street sign repaired or replaced; 105 hours of street sweeping covering 149 lane miles; and 43.36 tons of sweeper tailings hauled to the landfill.
- Storm drains: storm grates cleaned, sediment and debris removed from culvert inlets, and one storm drain box replaced.
- Utility locating (Blue Stakes): 102 locate requests, logging 54 hours.
The report's crew labor analysis lists hours by system, including Water System 479, Street Maint. 197, Storm Drain System 189 and Sewer System 186.
Engineering Report to City Council, November 2026
The Engineering Report (dated 11/13/2026) gives project status updates. The timelines below are the report's own stated expectations as of that date and may change.
Planning projects
- R&PP application for 100 acres (“public works yard, City park, City cemetery, etc.”): the report states that BLM advised the application “must undergo an additional federal review under the program's revised requirements,” that BLM indicated it is “the first Utah application to undergo the new review process,” and that BLM staff “cannot yet estimate how long the review will take.”
- Water and Irrigation Master Plan: staff is reviewing the consultant's initial draft and is looking to present it to the Council “in either January or February of 2027.”
- Transportation Master Plan: staff reviewed the initial draft and provided comments; the report states staff is “anticipating a presentation to council in December.”
Design projects
- Sewer Lift Station and Old Highway 91 Water Line Design: “nearing completion of design,” with remaining SCADA system details to be resolved before the project is advertised for bids.
- Lower Tuacahn Wash Sewer Project 2027: the report describes the line as extending “from Pioneer Parkway down to Snow Canyon High School” and serving Ivins and Santa Clara. The city issued an RFP for engineering design and bidding services and received three proposals; staff anticipated bringing a consultant selection recommendation to the City Council on Thursday, December 3, 2026.
- Tuacahn Tank Recoating: construction and bidding documents have been prepared; staff anticipated bidding the project in late November, with bids anticipated mid-December.
Construction projects
- Old Hwy 91 Landscape Median Curbing: a pre-construction meeting was held with the contractor, with a start anticipated early to mid-December, weather permitting.
- Public Works Yard West Parking Addition: work has begun, with completion anticipated by the end of November.
- Trail Gap Fill – BDR North Village to Docena: anticipated to start early December.
Developer projects under construction
The report states that Engineering is managing and supervising construction of these developer projects:
- Retreat at Snow Canyon (new): a pre-construction meeting was held in October; the developer was still fencing off sensitive areas that are to remain undisturbed. The report describes the project as involving “approximately 100 acres of previously undisturbed desert landscape,” with sensitive areas, “including the wash, lava formations, and portions of the existing ridgelines,” to be fenced off and protected, and states that “the vast majority, if not all, the soil will remain on site.”
- Solterra Phase 1: a pre-construction meeting was recently held; grading for Phase 1 anticipated in December.
- Percent complete, as listed: BDR North Village 100%; BDR Golf Village Phase 1, 2 & 3 100%; BDR Family Village 95%; BDR Pickleball Facilities 95%; Hidden Springs RV Resort 95%; Arava Phase 2 90%; BDR Water Park 75% (“just for the civil improvements”); Kwavasa Phase 3 60%; Aventura 40%; Chinle Cliffs 30%; Mohave Village 10%.
Other items on the November 19 agenda
The same agenda also listed, among other items, a quarterly report, a Planning Commission report, “Discuss and consider potential amendments to the Chinle Cliffs Development Agreement,” and “Discuss and consider approval of Resolution No. 2026-18R, a Resolution of Ivins City, Utah, approving an Interlocal Memorandum of Understanding regarding the Washington County, Utah, Criminal Task Force.” Outcomes of action items will be reported here once official minutes are posted. The full agenda was previewed in this earlier post.
Source documents
- Agenda, Ivins City Council, November 19, 2026
- Building Department Reports (PDF)
- Public Works Summary of Operations (PDF)
- Engineering Report (PDF)
- All supplemental documents for the November 19, 2026 City Council meeting
- November 19, 2026 City Council meeting on the Ivins Meetings page
For more about the city, see OwnUtah.com, Everything Ivins and the Ivins, Utah homes and real estate guide. Related coverage: Ivins Planning Commission Nov. 17 & City Council Nov. 19, 2026 Agendas, Ivins City Council Sets Dec. 3, 2026 Public Hearing on Home-Based Business Rules and Ivins City Council, Sept. 17, 2026: Old Highway 91 Median Curbing and City Manager Contract.
This is a summary only. For the authoritative version, check the official City of Ivins records at ivins.granicus.com and ivinsutah.gov, or contact the Ivins City Recorder at 435-628-0606.